Hillside building permits in Calabasas and LA County: soils reports, geotech and plan check

Table Of Contents

On a hillside lot, the permit starts in the ground. Before Building and Safety signs off on your plans, a soils engineer and an engineering geologist have to say the slope can carry the work, and your plans have to show what they recommend.

After that it is paperwork in a set order. I prepare the plans and file and pull the permit myself, so this is the order I walk through on a hillside job, for the City of Calabasas and for unincorporated LA County.

First question: city or county?

Find out who has your lot before anything is drawn.

Inside Calabasas city limits, the city reviews it: Planning for the hillside and ridgeline rules, Building and Safety for plan check.

Outside city limits, in unincorporated LA County (Topanga is one example), it goes through LA County Public Works Building and Safety, at the Calabasas-Malibu district office on Agoura Road. Same canyons, different rulebook.

The soils and geology report

This is the document the whole job hangs on.

In Calabasas, the Building and Safety submittal checklist lists a geology/soils report with the plans and structural calcs. A retaining wall over 4 feet needs a soils report that backs up its design numbers, and it gets its own permit.

In LA County, the plan checker decides if your job goes to the county’s Geotechnical and Materials Engineering Division (GMED). The report has to be signed and stamped by a California Certified Engineering Geologist and by a Geotechnical Engineer, or a Civil Engineer with geotechnical experience.

A few county rules catch people out:

  • The report has to be less than one year old when it goes in. Older than that, the consultants write an update.
  • Slope stability calculations are generally required when a slope is steeper than 2 to 1, or taller than 30 feet.
  • Additions, new stories, basements, decks and pools tied to the house need foundation recommendations, including how the new work loads the old foundation.

A licensed third party does the soils and geology report. I don’t write it. I design around it. The foundation type, the retaining walls and sometimes where the house can sit all come out of that report, so it should be in hand before the design is final.

Calabasas hillside and ridgeline rules

Calabasas has its own hillside standards in the Development Code, Section 17.20.150. They apply to any site with a natural slope over 10 percent, or with a ridgeline on it.

Two more lines on the map:

  • Significant ridgelines. New structures on a mapped significant ridgeline have a 50-foot setback rule. Building closer has needed a variance, though a 2016 change took minor additions of 1,200 square feet or less out of that.
  • Scenic corridors. Projects within 500 feet of Mulholland Highway, Las Virgenes Road, Old Topanga Canyon Road or the Ventura Freeway fall under the city’s Scenic Corridor Development Guidelines.

Grading permit and plan check

In Calabasas, Section 17.52.030 of the Development Code requires a grading permit for any excavation that isn’t exempt. The city’s application asks for your cut, fill, over-excavation and import/export numbers in cubic yards, and the names and licence numbers of the civil engineer and the geologist or geotechnical engineer. Once grading is approved, the site can get its building permits.

In LA County, the referral sheet lists every agency that has to approve your job before the permit is issued. All of those approvals go in at least 48 hours before the permit is issued. On some jobs the county also requires rough grade approval before it will issue the building permit.

Once you dig, the county’s grading guide sets the rules:

  • The soils engineer has to be on site while fill goes in and gets compacted.
  • From October 15 to April 15 (the rainy season), erosion control has to be in place.
  • A grading permit expires if work does not start within 180 days, or if work stops for 180 days.

Fire zone rules on top

A 2023 letter from the LA County Fire Department says all of Calabasas is a High or Very High Fire Hazard Severity Zone. The city says those properties may fall under Chapter 7A of the California Building Code (wildfire-resistant construction).

In a Fire Hazard Severity Zone, LA County Fire needs an approved Fuel Modification Plan before the building permit for:

  • new construction
  • remodels of 50 percent or more
  • some outbuildings and accessory structures over 120 square feet

After you move in, brush clearance is yearly: out to 100 feet under the county’s 2023 notice, and up to 200 feet in extra hazardous areas.

Why I can’t promise you a timeline

None of these agencies publishes a fixed timeline for a hillside permit, and I won’t make one up. It depends on how many agencies are on your referral sheet, how many rounds of corrections each one sends back, and whether the soils report has to be redone. On county jobs, the referral sheet itself says the review clock stops while an outside agency’s approval is outstanding.

What shortens it is a first submittal where the soils report, grading plan and architectural plans all agree.

How I work on a hillside job

Vision In Design Inc is a design-build company. If you call me for an estimate, I can’t give you an honest number until I know what you want to build. So I do a preliminary design first. Once you like the design, I give you the estimate.

If you go ahead, I design the project, prepare all the plans, and file and pull the building permit. The third-party work is separate from mine: structural engineering, surveying, the soil and geology report if one is required, and the city or county permit fees. Then we build what was drawn and permitted.

More on architectural design and permit drawings and on hillside construction. If you have a sloped lot in Calabasas or the hills around it, call me at (818) 645-1129. Have the address ready, and the soils report if you already have one. ## FAQ

Do I need a soils report to build on a hillside in Calabasas?

Plan on it. The city’s submittal checklist lists a geology/soils report, and retaining walls over 4 feet need one. Ask the city counter what your scope needs.

What is the difference between the engineering geologist and the soils engineer?

LA County’s grading guide splits the job. The soils engineer watches the ground get prepared and tests that the fill is compacted. The engineering geologist inspects the bedrock as it is dug and checks it matches the approved report.

How long is a geotechnical report good for?

For LA County review, one year from submittal. After that, the consultants write an update.

Does a deck or pool on a slope need geotechnical review?

In LA County, the geotechnical manual calls out decks and pools near slopes for slope stability review, and pools must meet the code setback or a bigger one the geotechnical engineer sets.

Vision In Design Inc Logo
Vision In Design Inc
Don't settle for ordinary—bring your vision to life with the dedicated design-build experts at Vision In Design Inc. Request your personalized consultation today.